CEEE-GT – Santa Rosa 1 Substation- 230 kV

CEEE-GT - Santa Rosa 1 Substation- 230 kV img1



CEEE-GT - Santa Rosa 1 Substation- 230 kV img2

HIGHLIGHTS :

Place: Santa Rosa,RS – Brazil
Beginning: 11/2014 End: 04/2016
Value: R$ 7 million
230/69 kV – 2×83 MVA
EL – Três de Maio Module
EL – Giruá Module
Modules of the New TR – 69/23 kV – 25 MVA
New Bus of 23 kV

The project:

The supply of this project was made by VISION in turnkey regime reinforced the electrical system of the northwest region of the State of Rio Grande do Sul. The scope includes: the complete design, equipment and services for the line entry bay, the new transformer bay and Feeders.