VISION ENERGIZES NEW SECTORS OF SE COLINAS 500 KV / 138 KV

VISION energized on June 6, 2021 the 500 kV and 138 kV sectors of the Colinas substation owned by ELETRONORTE, in the state of TOCANTINS.
VISION signed a contract as an EPC and was responsible for the turnkey supply of the entire project and work of lot 11 of the ANEEL 002/2018 transmission auction, won by LYON ENERGIA.
The scope included a new 138 kV yard, 7 single-phase 500 / 138 kV transformers of 60 MVA each, in addition to the replacement of differential protection and extension, of buses A and B in the 500 kV sector.
The substation is located in the municipality of Colinas do Tocantins, very close to the limit with the municipality of Palmeirante. In the future, this substation will be part of the transmission system of UHE Belo Monte, in Pará.