VISION GROUP SIGNS CONTRACT WITH CEMIG FOR IMPLEMENTATION OF BETTERNESS AND REINFORCEMENT ON EMBORCAÇÃO 500KV SUBSTATION

VISION GROUP SIGNS CONTRACT WITH CEMIG FOR IMPLEMENTATION OF BETTERNESS AND REINFORCEMENT ON EMBORCAÇÃO 500KV SUBSTATION

03/06/2019

Execution of whole project includes substitution, relocation and installation of  full sections (bays/modules) of 500kV and 138kV, with supply of protection and control system, lightning rod... [Learn More...]



CEMIG’S CONFINS SE IS SUCESSFULLY ENERGIZED

138kV substation CONFINS 1 was energized by Grupo VISION. The scope of supply turnkey comprehends, among others, a compact hybrid switchgear module (MMHC) SF6 gas-insulated 145kV/40kA 2.000A, a 138KV/13,... [Learn More...]


VISION GROUP SIGNS CONTRACT WITH ARCELOR MITTAL – MINA DO ANDRADE’S EXPANSION PROJECT

24/05/2019

VISION Group signed a contract with ARCELOR MITTAL for the supply of two E-houses and automation systems for Mina do Andrade expansion, located on João Monlevade, MG. The biggest E-house is going to... [Learn More...]


VISION ENERGIZES SOLAR PLANTS SUBSTATION GUIMARÂNIAS I AND II.

Substation is part of solar complex of Guimarânia with over 180 hectares and utilizes 126 thousand solar panels with production capacity of up to 60 MW.

E-house for Anglo American briquetting project was supplied in less than 80 days from VISION Group, counted from contract signature to initial date of transport. Scope consisted of project supply, f... [Learn More...]