The VISION Group Delivers the F & S AGRISOLUTIONS’s Works

The VISION Group successfully delivers another important work in the Center West of Brazil with an F&S AGRISOLUTIONS plant in Lucas do Rio Verde – MT. The turnkey contract included the supply of the entire system of automation, drives, control, distribution and protection, low and medium voltage. F&S AGRISOLUTIONSthe is the first fully ethanol industry […]

Energizing the São Sebastião do Oeste substation of CEMIG.

The VISION group successfully completed the energy of the São Sebastião do Oeste substation of CEMIG. This 138kV / 25MVA (SE) substation uses hybrid switchgear module – GIS (Gas Insulated Substation), technology that allows high reliability, 90% less maintenance costs among other gains compared to conventional. SE São Sebastião do Oeste is a first company […]

CEMIG – São Sebastião do Oeste Substation – HGIS – 138KV – 25MVA

HIGHLIGHTS : Place: São Sebastião do Oeste, MG – Brazil Beginning: 04/2016 End: 07/2017 Value: R$ 12 million HGIS – SF6 Compact Hybrid Maneuver Module São Sebastião do Oeste was the first SE acquired by CEMIG with E-house 10 Cubicles / Feeders 1250A / 13,8KV 1250A/13,8KV The project: The São Sebastião do Oeste substation at […]

VALE – North Logistics capacity – E-House – 2,500 kVA

HIGHLIGHTS : Location: Canaã dos Carajás, PA – Brazil Start: 09/2015 Ends: 07/2016 Value: R$ 7 Million Energy Supply for Lighting, Telecommunication and Signaling Switchgear of MV 1 x 34,5 kV e 8 x 17,5 kV CLP (S7-300), FDI and Supervision System -SCADA CCTV, Access Control, SDCI, among others Civil Construction and Electromechanical Assembly Commissioning, […]

Energizing the Nova Ponte Substation

The VISION Group carried out the energization of the Nova Ponte substation. The scope of supply includes, among others, two MMHC insulated SF6 145KV / 40KA 2000A (GIS – Gas Insulated Substation), digital protection and control system in IEC61850, MCP, SPDA, design, electromechanical assembly, civil works and commissioning . The hybrid section substation is located […]

VISION completed assembly of the first substation of CEMIG to use E-house

VISION completed assembly and commissioning of the E-house of the São Sebastião do Oeste substation. This 138KV / 25MVA substation, which also uses hybrid modules (GIS), is CEMIG’s first substation to use Eletrocentro (modular, easily transportable, metallic electrical room) that will contain all the protection and distribution of the substation in place of the conventional […]